Action Date | Action Description |
---|---|
Jan 13, 2012 | Assent Application Received |
Jan 16, 2012 | Administrative Review for Completeness |
Jan 17, 2012 | Team Review for Completeness |
Jan 17, 2012 | Team Review for Completeness |
Jan 17, 2012 | Application Accepted |
Feb 06, 2012 | HPHC Historical Preservation No Effect |
Feb 24, 2012 | Plans Received |
Mar 08, 2012 | Plans Received |
Mar 08, 2012 | Biologist Report |
Mar 09, 2012 | Engineering Report |
Mar 13, 2012 | Typist for Processing |
Mar 13, 2012 | Permit Approved |
Mar 14, 2012 | Executive Sign Off |
Mar 14, 2012 | Sent to Photo Copy |
Mar 27, 2012 | Land Evidence Date |
Mar 30, 2012 | Commencement of Work Notice received |