Action Date | Action Description |
---|---|
Feb 07, 2012 | Assent Application Received |
Feb 07, 2012 | Administrative Review for Completeness |
Feb 09, 2012 | Team Review for Completeness |
Feb 09, 2012 | Team Review for Completeness |
Feb 09, 2012 | Application Accepted |
Feb 24, 2012 | Plans Received |
Mar 06, 2012 | HPHC Historical Preservation No Effect |
Apr 12, 2012 | Plans Received |
Apr 16, 2012 | Typist for Processing |
Apr 16, 2012 | Biologist Report |
Apr 16, 2012 | Engineering Report |
Apr 16, 2012 | Permit Approved |
Apr 17, 2012 | Plans Received |
Apr 17, 2012 | Executive Sign Off |
Apr 17, 2012 | Sent to Photo Copy |