Action Date | Action Description |
---|---|
Feb 20, 2012 | Assent Application Received |
Feb 20, 2012 | Administrative Review for Completeness |
Feb 27, 2012 | Team Review for Completeness |
Feb 27, 2012 | Team Review for Completeness |
Feb 27, 2012 | Application Accepted |
Mar 07, 2012 | Engineering Report |
Mar 07, 2012 | Biologist Report |
Mar 08, 2012 | Typist for Processing |
Mar 08, 2012 | Permit Approved |
Mar 15, 2012 | Executive Sign Off |
Mar 15, 2012 | Sent to Photo Copy |
Mar 22, 2012 | Land Evidence Date |
Apr 03, 2012 | HPHC Historical Preservation No Effect |
Aug 05, 2013 | Letter of Authorization |