Action Date | Action Description |
---|---|
Jul 02, 2012 | Assent Application Received |
Jul 03, 2012 | Administrative Review for Completeness |
Aug 01, 2012 | Team Review for Completeness |
Aug 01, 2012 | Team Review for Completeness |
Aug 01, 2012 | Application Accepted |
Aug 20, 2012 | 30 day Public Notice Issued |
Aug 20, 2012 | Public Notice End Date |
Sep 01, 2012 | HPHC Historical Preservation No Effect |
Sep 27, 2012 | Additional Information Received |
Oct 15, 2012 | Correspondence Received |
Oct 17, 2012 | Additional Information Received |
Oct 24, 2012 | Biologist Report |
Oct 24, 2012 | Engineering Report |
Oct 31, 2012 | Supervisor Biologist SignOff |
Oct 31, 2012 | Supervisor Engineer SignOff |
Nov 01, 2012 | Executive Signoff of Staff Reports |
Nov 20, 2012 | Ready to Schedule Semi-Monthly Meeting |
Nov 26, 2012 | US Army Corps of Engineers Approval Received |
Nov 27, 2012 | Semi-Monthly Meeting Held |
Nov 27, 2012 | Council Approval Granted |
Nov 27, 2012 | Semi-Monthly Meeting Date Scheduled |
Nov 27, 2012 | Mail Agenda Notice |
Dec 11, 2012 | Legal Response/Decision |
Dec 11, 2012 | 30 Day Appeal Notification to Owner |
Dec 12, 2012 | Stipulation Package from Biologist |
Dec 12, 2012 | Stipulation Package by Engineer |
Dec 19, 2012 | Typist for Processing |
Dec 19, 2012 | Executive Sign Off |
Dec 19, 2012 | Sent to Photo Copy |
Dec 19, 2012 | Permit Approved |
Jan 04, 2013 | Duplicate Original Assent requested/mailed |
Jan 18, 2013 | Land Evidence Date |
Jan 31, 2013 | RIPDES Permit Issued |