Action Date | Action Description |
---|---|
Jul 02, 2012 | Assent Application Received |
Jul 03, 2012 | Administrative Review for Completeness |
Jul 10, 2012 | Team Review for Completeness |
Jul 10, 2012 | Team Review for Completeness |
Jul 10, 2012 | Deficient Application - Owner Notification Sent |
Jan 24, 2013 | Deficiency Response Received |
Jan 28, 2013 | Team Review for Completeness |
Jan 28, 2013 | Team Review for Completeness |
Jan 28, 2013 | Application Accepted |
Jan 29, 2013 | HPHC Historical Preservation No Effect |
Apr 03, 2013 | Biologist Report |
Apr 03, 2013 | Engineering Report |
Apr 04, 2013 | Typist for Processing |
Apr 04, 2013 | Permit Approved |
Apr 05, 2013 | Executive Sign Off |
Apr 05, 2013 | Sent to Photo Copy |
Jul 01, 2013 | Land Evidence Date |