Action Date | Action Description |
---|---|
Aug 17, 2012 | Assent Application Received |
Aug 17, 2012 | Administrative Review for Completeness |
Aug 20, 2012 | Team Review for Completeness |
Aug 20, 2012 | Team Review for Completeness |
Aug 20, 2012 | Application Accepted |
Aug 31, 2012 | Engineering Report |
Aug 31, 2012 | Biologist Report |
Sep 05, 2012 | Typist for Processing |
Sep 05, 2012 | Permit Approved |
Sep 06, 2012 | Executive Sign Off |
Sep 06, 2012 | Sent to Photo Copy |
Sep 12, 2012 | HPHC Historical Preservation No Effect |
Nov 02, 2012 | Land Evidence Date |