Action Date | Action Description |
---|---|
Sep 10, 2012 | Assent Application Received |
Sep 11, 2012 | Administrative Review for Completeness |
Sep 17, 2012 | Team Review for Completeness |
Sep 17, 2012 | Team Review for Completeness |
Sep 17, 2012 | Deficient Application - Owner Notification Sent |
Sep 20, 2012 | Deficient Application Picked Up |
Oct 15, 2012 | Deficiency Response Received |
Oct 18, 2012 | Team Review for Completeness |
Oct 18, 2012 | Team Review for Completeness |
Oct 18, 2012 | Application Accepted |
Nov 01, 2012 | HPHC Historical Preservation No Effect |
Jan 28, 2013 | Additional Information Received |
Mar 04, 2013 | Additional Information Received |
Mar 11, 2013 | Engineering Report |
Mar 12, 2013 | Biologist Report |
Mar 13, 2013 | Typist for Processing |
Mar 14, 2013 | Executive Sign Off |
Mar 14, 2013 | Sent to Photo Copy |
Mar 14, 2013 | Permit Approved |
Mar 18, 2013 | Land Evidence Date |
Aug 09, 2016 | Expiration of Assent/End of Tolling Legislation |
Jun 12, 2018 | Expiration of Assent/End of Tolling Legislation |
Apr 10, 2019 | Extension of Permit Request |
May 24, 2019 | Enforcement Compliance Inspection Required |
May 28, 2019 | Process Extension |
May 28, 2019 | Extension Approved |
Aug 05, 2021 | Phone Call |