Action Date | Action Description |
---|---|
Sep 17, 2012 | Preliminary Determination Request (Coastal) |
Sep 17, 2012 | Administrative Review for Completeness |
Sep 19, 2012 | Team Review for Completeness |
Sep 19, 2012 | Team Review for Completeness |
Sep 19, 2012 | Application Accepted |
Sep 27, 2012 | HPHC Historical Preservation No Effect |
Jan 07, 2013 | Category A assigned |
Jan 07, 2013 | Biologist Report |
Jan 07, 2013 | Engineering Report |
Jan 08, 2013 | Typist for Processing |
Jan 08, 2013 | Executive Sign Off |
Jan 08, 2013 | Permit Approved |
Jan 10, 2013 | Sent to Photo Copy |
Jun 28, 2013 | Correspondence Received |
Jun 28, 2013 | Correspondence Received |
Jul 09, 2013 | Land Evidence Date |