Action Date | Action Description |
---|---|
Oct 11, 2012 | Assent Application Received |
Oct 12, 2012 | Administrative Review for Completeness |
Oct 15, 2012 | Team Review for Completeness |
Oct 15, 2012 | Team Review for Completeness |
Oct 15, 2012 | Application Accepted |
Nov 01, 2012 | HPHC Historical Preservation No Effect |
Dec 12, 2012 | Additional Information Requested from Applicant |
Dec 24, 2012 | Plans Received |
Dec 28, 2012 | Engineering Report |
Jan 02, 2013 | Biologist Report |
Jan 03, 2013 | Typist for Processing |
Jan 03, 2013 | Permit Approved |
Jan 04, 2013 | Executive Sign Off |
Jan 04, 2013 | Sent to Photo Copy |
Jan 22, 2013 | Land Evidence Date |