Action Date | Action Description |
---|---|
Mar 04, 2013 | Assent Application Received |
Mar 05, 2013 | Administrative Review for Completeness |
Mar 11, 2013 | Team Review for Completeness |
Mar 11, 2013 | Team Review for Completeness |
Mar 11, 2013 | Application Accepted |
Mar 19, 2013 | HPHC Historical Preservation No Effect |
Apr 08, 2013 | 30 day Public Notice Issued |
May 08, 2013 | Public Notice End Date |
May 14, 2013 | Correspondence Received |
May 30, 2013 | US Army Corps of Engineers Approval Received |
Jul 11, 2013 | Biologist Report |
Jul 11, 2013 | Engineering Report |
Jul 15, 2013 | Typist for Processing |
Jul 15, 2013 | Executive Sign Off |
Jul 15, 2013 | Sent to Photo Copy |
Jul 15, 2013 | Permit Approved |
Jul 29, 2013 | Land Evidence Date |