Action Date | Action Description |
---|---|
Mar 15, 2013 | Assent Application Received |
Mar 18, 2013 | Administrative Review for Completeness |
Mar 19, 2013 | Team Review for Completeness |
Mar 19, 2013 | Team Review for Completeness |
Mar 19, 2013 | Application Accepted |
Apr 05, 2013 | HPHC Historical Preservation No Effect |
Jul 15, 2013 | Additional Information Received |
Jul 18, 2013 | Additional Information Received |
Jul 22, 2013 | Biologist Report |
Jul 22, 2013 | Engineering Report |
Jul 24, 2013 | Typist for Processing |
Jul 24, 2013 | Executive Sign Off |
Jul 24, 2013 | Sent to Photo Copy |
Jul 24, 2013 | Permit Approved |
Aug 13, 2013 | Land Evidence Date |