Action Date | Action Description |
---|---|
Aug 07, 2013 | Team Review for Completeness |
Aug 07, 2013 | Application Accepted |
Aug 07, 2013 | Assent Application Received |
Aug 07, 2013 | Administrative Review for Completeness |
Aug 29, 2013 | Engineering Report |
Aug 29, 2013 | Permit Approved |
Aug 29, 2013 | Typist for Processing |
Sep 03, 2013 | Executive Sign Off |
Sep 03, 2013 | Sent to Photo Copy |
Sep 18, 2013 | HPHC Historical Preservation No Effect |