Action Date | Action Description |
---|---|
Sep 25, 2013 | Assent Application Received |
Sep 27, 2013 | Administrative Review for Completeness |
Sep 27, 2013 | Team Review for Completeness |
Oct 04, 2013 | Deficient Application - Owner Notification Sent |
Dec 26, 2013 | Plans Received |
Dec 26, 2013 | Correspondence Received |
Dec 26, 2013 | Deficiency Response Received |
Dec 26, 2013 | Team Review for Completeness |
Dec 26, 2013 | Application Accepted |
Jan 09, 2014 | 30 day Public Notice Issued |
Feb 09, 2014 | Public Notice End Date |
Mar 14, 2014 | Additional Information Received |
Mar 27, 2014 | Biologist Report |
Apr 07, 2014 | US Army Corps of Engineers Approval Received |
Apr 11, 2014 | Supervisor Biologist SignOff |
Apr 14, 2014 | Supervisor Engineer SignOff |
Apr 14, 2014 | Executive Signoff of Staff Reports |
May 01, 2014 | Special Exception Public Hearing Notice mailed |
May 07, 2014 | Entry of Appearance Received |
Jun 24, 2014 | Council Approval Granted |
Jun 24, 2014 | Semi-Monthly Meeting Date Scheduled |
Jun 24, 2014 | Semi-Monthly Meeting Held |
Jul 23, 2014 | 30 Day Appeal Notification to Owner |
Jul 23, 2014 | Legal Response/Decision |
Jul 30, 2014 | Stipulation Package from Biologist |
Jul 31, 2014 | Permit Approved |
Jul 31, 2014 | Typist for Processing |
Aug 01, 2014 | Executive Sign Off |
Aug 01, 2014 | Sent to Photo Copy |
Aug 12, 2014 | Land Evidence Date |