Action Date | Action Description |
---|---|
Dec 24, 2013 | Assent Application Received |
Dec 24, 2013 | Administrative Review for Completeness |
Dec 31, 2013 | Team Review for Completeness |
Dec 31, 2013 | Application Accepted |
Feb 20, 2014 | HPHC Historical Preservation No Effect |
Feb 25, 2014 | Additional Information Received |
Mar 07, 2014 | Plans Received |
Apr 07, 2014 | Plans Received |
Apr 14, 2014 | Biologist Report |
Apr 29, 2014 | Typist for Processing |
Apr 29, 2014 | Executive Sign Off |
Apr 29, 2014 | Sent to Photo Copy |
Apr 29, 2014 | Permit Approved |
May 20, 2014 | Typist for Processing |
May 20, 2014 | Typist for Processing |
May 20, 2014 | Assent Correction Mailed |
May 28, 2014 | Executive Sign Off |
May 28, 2014 | Sent to Photo Copy |
May 30, 2014 | Executive Sign Off |
May 30, 2014 | Sent to Photo Copy |
Jun 04, 2014 | Land Evidence Date |
Oct 14, 2021 | Meeting Held |