Action Date | Action Description |
---|---|
Oct 06, 2014 | Assent Application Received |
Oct 06, 2014 | Administrative Review for Completeness |
Oct 08, 2014 | Team Review for Completeness |
Oct 08, 2014 | Team Review for Completeness |
Oct 08, 2014 | Application Accepted |
Oct 22, 2014 | 30 day Public Notice Issued |
Nov 07, 2014 | HPHC Historical Preservation No Effect |
Nov 22, 2014 | Public Notice End Date |
Nov 24, 2014 | US Army Corps of Engineers Approval Received |
Jan 22, 2015 | Plans Received |
Feb 06, 2015 | Dock Meeting Scheduled (Admin) |
Feb 18, 2015 | Dock Meeting -- Approval |
Feb 23, 2015 | Engineering Report |
Feb 23, 2015 | Biologist Report |
Feb 24, 2015 | Typist for Processing |
Feb 26, 2015 | Executive Sign Off |
Feb 26, 2015 | Sent to Photo Copy |
Feb 26, 2015 | Permit Approved |
Mar 24, 2015 | Land Evidence Date |