Action Date | Action Description |
---|---|
Nov 05, 2014 | Assent Application Received |
Nov 05, 2014 | Administrative Review for Completeness |
Nov 07, 2014 | Team Review for Completeness |
Nov 07, 2014 | Team Review for Completeness |
Nov 07, 2014 | Application Accepted |
Nov 14, 2014 | HPHC Historical Preservation No Effect |
Jan 06, 2015 | Correspondence Received |
Jan 07, 2015 | 30 day Public Notice Issued |
Feb 07, 2015 | Public Notice End Date |
Feb 18, 2015 | Dock/1.1.6 Review approval |
Mar 17, 2015 | Objections/Comments Received |
Mar 30, 2015 | US Army Corps of Engineers Approval Received |
Apr 17, 2015 | Objection withdrawal received |
Apr 22, 2015 | Biologist Report |
Apr 22, 2015 | Engineering Report |
Apr 23, 2015 | Typist for Processing |
Apr 23, 2015 | Executive Sign Off |
Apr 23, 2015 | Sent to Photo Copy |
Apr 23, 2015 | Permit Approved |
Apr 28, 2015 | Land Evidence Date |
Oct 13, 2017 | Comments Received |