Action Date | Action Description |
---|---|
Dec 24, 2014 | Assent Application Received |
Dec 24, 2014 | Administrative Review for Completeness |
Jan 05, 2015 | Team Review for Completeness |
Jan 05, 2015 | Application Accepted |
Jan 05, 2015 | Category B assigned |
Feb 06, 2015 | HPHC Historical Preservation No Effect |
Apr 02, 2015 | Correspondence Received |
Apr 06, 2015 | 30 day Public Notice Issued |
May 06, 2015 | Public Notice End Date |
May 13, 2015 | Note to File |
Jul 10, 2015 | Plans Received |
Jul 23, 2015 | Plans Received |
Jul 24, 2015 | Engineering Report |
Jul 24, 2015 | Biologist Report |
Jul 24, 2015 | Supervisor Engineer SignOff |
Jul 27, 2015 | Supervisor Biologist SignOff |
Jul 28, 2015 | Executive Signoff of Staff Reports |
Jul 28, 2015 | Special Exception Public Hearing Notice mailed |
Sep 08, 2015 | Semi-Monthly Meeting Date Scheduled |
Oct 13, 2015 | Semi-Monthly Meeting Date Scheduled |
Oct 13, 2015 | Council Approval Granted |
Oct 13, 2015 | Stipulation Package from Biologist |
Oct 13, 2015 | Stipulation Package by Engineer |
Oct 20, 2015 | Legal Response/Decision |
Oct 20, 2015 | 30 Day Appeal Notification to Owner |
Nov 30, 2015 | Typist for Processing |
Dec 02, 2015 | Executive Sign Off |
Dec 02, 2015 | Sent to Photo Copy |
Dec 02, 2015 | Permit Approved |
Apr 18, 2016 | Duplicate Original Assent requested/mailed |
May 12, 2016 | Land Evidence Date |