Action Date | Action Description |
---|---|
Jan 21, 2015 | Assent Application Received |
Jan 21, 2015 | Administrative Review for Completeness |
Jan 30, 2015 | Team Review for Completeness |
Jan 30, 2015 | Application Accepted |
Feb 03, 2015 | Engineering Report |
Feb 19, 2015 | HPHC Historical Preservation No Effect |
Feb 20, 2015 | 30 day Public Notice Issued |
Mar 20, 2015 | Public Notice End Date |
Apr 06, 2015 | Biologist Report |
May 04, 2015 | US Army Corps of Engineers Approval Received |
Jun 16, 2015 | Plans Received |
Jun 18, 2015 | Typist for Processing |
Jun 19, 2015 | Executive Sign Off |
Jun 19, 2015 | Sent to Photo Copy |
Jun 19, 2015 | Permit Approved |
Dec 03, 2015 | Land Evidence Date |
Dec 30, 2015 | Category A* (Docks) |