Action Date | Action Description |
---|---|
May 08, 2015 | Assent Application Received |
May 08, 2015 | Administrative Review for Completeness |
May 11, 2015 | Correspondence Received |
May 13, 2015 | Application Accepted |
May 13, 2015 | Team Review for Completeness |
Jun 23, 2015 | 30 day Public Notice Issued |
Jul 08, 2015 | Meeting Held |
Jul 09, 2015 | Objections/Comments Received |
Jul 15, 2015 | Correspondence Mailed/Faxed/E-mailed |
Jul 23, 2015 | Public Notice End Date |
Jul 24, 2015 | Correspondence Received |
Aug 31, 2015 | Plans Received |
Oct 09, 2015 | Plans Received |
Nov 16, 2015 | Mail Agenda Notice |
Nov 16, 2015 | Meeting Held |
Nov 25, 2015 | Plans Received |
Dec 01, 2015 | Biologist Report |
Dec 01, 2015 | Engineering Report |
Dec 02, 2015 | Supervisor Engineer SignOff |
Dec 02, 2015 | Executive Signoff of Staff Reports |
Dec 03, 2015 | Water Quality Certification |
Dec 08, 2015 | Council Approval Granted |
Dec 08, 2015 | Semi-Monthly Meeting Date Scheduled |
Jan 12, 2016 | Legal Response/Decision |
Jan 12, 2016 | 30 Day Appeal Notification to Owner |
Mar 03, 2016 | Correspondence Received |
Mar 10, 2016 | Stipulation Package from Biologist |
Mar 10, 2016 | Stipulation Package by Engineer |
Mar 31, 2016 | Correspondence Received |
Apr 22, 2016 | Typist for Processing |
Apr 25, 2016 | Executive Sign Off |
Apr 25, 2016 | Sent to Photo Copy |
Apr 25, 2016 | Permit Approved |
May 02, 2016 | Conservation Easement and Restrictions Requested |
May 05, 2016 | Land Evidence Date |
Jul 05, 2017 | Plans Received |
Jul 17, 2017 | Correspondence Received |
Aug 25, 2017 | Modification Request |
Aug 25, 2017 | Administrative Review for Completeness |
Aug 29, 2017 | Team Review for Completeness |
Aug 29, 2017 | Application Accepted |
Sep 13, 2017 | HPHC Historical Preservation No Effect |
Oct 13, 2017 | Plans Received |
Nov 15, 2017 | Plans Received |
Nov 20, 2017 | Additional Information Received |
Dec 08, 2017 | Modification Approved |
Dec 08, 2017 | Biologist Report |
Dec 08, 2017 | Engineering Report |
Mar 09, 2018 | Land Evidence Date |
Apr 18, 2018 | Modification Request |
Apr 18, 2018 | Administrative Review for Completeness |
Apr 26, 2018 | HPHC Historical Preservation No Effect |
Apr 26, 2018 | Team Review for Completeness |
Apr 26, 2018 | Application Accepted |
May 25, 2018 | Biologist Report |
May 25, 2018 | Engineering Report |
May 29, 2018 | Expiration of Assent/End of Tolling Legislation |
May 29, 2018 | Typist for Processing |
May 29, 2018 | Executive Sign Off |
May 29, 2018 | Sent to Photo Copy |
May 29, 2018 | Modification Approved |
May 29, 2018 | Permit Approved |
Jun 12, 2018 | HPHC Historical Preservation Comments/Concerns |
Jun 15, 2018 | Land Evidence Date |
Aug 30, 2018 | Note to File |
Mar 05, 2019 | Note to File |
Jun 10, 2019 | Additional Information Received |