Action Date | Action Description |
---|---|
Dec 11, 2015 | Assent Application Received |
Dec 15, 2015 | Administrative Review for Completeness |
Dec 28, 2015 | HPHC Historical Preservation No Effect |
Dec 30, 2015 | Category A* (Docks) |
Jan 13, 2016 | Application Accepted |
Jan 13, 2016 | Team Review for Completeness |
Jan 13, 2016 | Team Review for Completeness |
Feb 09, 2016 | Additional Information Requested from Applicant |
Apr 14, 2016 | Plans Received |
Apr 15, 2016 | 30 day Public Notice Issued |
May 18, 2016 | Public Notice End Date |
Jun 06, 2016 | Plans Received |
Jun 23, 2016 | Plans Received |
Jun 27, 2016 | US Army Corps of Engineers Approval Received |
Jul 22, 2016 | Additional Information Received |
Aug 03, 2016 | Dock Meeting -- Approval |
Aug 17, 2016 | Correspondence Received |
Aug 17, 2016 | Biologist Report |
Aug 22, 2016 | Engineering Report |
Aug 24, 2016 | Typist for Processing |
Aug 25, 2016 | Executive Sign Off |
Aug 25, 2016 | Sent to Photo Copy |
Aug 25, 2016 | Permit Approved |
Aug 26, 2016 | Land Evidence Date |