Action Date |
Action Description |
|
Enforcement Compliance Inspection Required |
Feb 09, 2016 |
Assent Application Received |
Feb 09, 2016 |
Administrative Review for Completeness |
Feb 10, 2016 |
Team Review for Completeness |
Feb 10, 2016 |
Team Review for Completeness |
Feb 10, 2016 |
Application Accepted |
Mar 01, 2016 |
Additional Information Requested from Applicant |
Mar 08, 2016 |
HPHC Historical Preservation No Effect |
Mar 11, 2016 |
Additional Information Received |
Mar 21, 2016 |
30 day Public Notice Issued |
Apr 13, 2016 |
Objections/Comments Received |
Apr 20, 2016 |
Objections/Comments Received |
Apr 21, 2016 |
Public Notice End Date |
Oct 26, 2016 |
Additional Information Requested from Applicant |
Dec 05, 2016 |
30-Day Notification of Cancellation letter |
Dec 21, 2016 |
Plans Received |
Apr 13, 2017 |
Mail Agenda Notice |
Apr 13, 2017 |
Entry of Appearance Received |
Apr 24, 2017 |
Letter of Support for Project |
Apr 28, 2017 |
Biologist Report |
Apr 28, 2017 |
Engineering Report |
May 02, 2017 |
Correspondence Received |
May 09, 2017 |
Council Approval Granted |
May 09, 2017 |
Semi-Monthly Meeting Date Scheduled |
Oct 18, 2017 |
Legal Response/Decision |
Oct 18, 2017 |
30 Day Appeal Notification to Owner |
Jul 25, 2018 |
Stipulation Package from Biologist |
Jul 26, 2018 |
Stipulation Package by Engineer |
Jul 26, 2018 |
Typist for Processing |
Jul 26, 2018 |
Executive Sign Off |
Jul 26, 2018 |
Sent to Photo Copy |
Jul 26, 2018 |
Permit Approved |
Aug 14, 2018 |
Land Evidence Date |
Apr 19, 2021 |
Extension of Permit Request |
Apr 29, 2021 |
Enforcement Compliance Inspection Required |
May 13, 2021 |
Process Extension |
May 13, 2021 |
Extension Approved |
Jul 21, 2021 |
Commencement of Work Notice received |
Mar 22, 2022 |
Modification Request |
Apr 15, 2022 |
Administrative Review for Completeness |
Apr 21, 2022 |
Bio Team Review for Completeness |
Apr 22, 2022 |
Project Manager |
Apr 25, 2022 |
Extension of Permit Request |
May 10, 2022 |
Additional Information Requested from Applicant |
May 11, 2022 |
HPHC Historical Preservation No Effect |
May 11, 2022 |
HPHC Review Pending |
May 23, 2022 |
Biologist Report |
May 24, 2022 |
Modification Approved |
Jun 01, 2022 |
Land Evidence Date |
Nov 25, 2022 |
Enforcement Compliance Inspection Required |
Nov 29, 2022 |
Process Extension |
Nov 30, 2022 |
Extension Approved |
Feb 27, 2023 |
Extension of Permit Request |
May 22, 2023 |
Enforcement Compliance Inspection Required |
Jul 07, 2023 |
Process Extension |
Jul 07, 2023 |
Extension Approved |
May 23, 2024 |
Extension of Permit Request |