Action Date | Action Description |
---|---|
Apr 20, 2017 | Assent Application Received |
Apr 20, 2017 | Administrative Review for Completeness |
May 05, 2017 | Team Review for Completeness |
May 05, 2017 | Team Review for Completeness |
May 05, 2017 | Application Accepted |
May 25, 2017 | HPHC Historical Preservation No Effect |
May 31, 2017 | Biologist Report |
May 31, 2017 | Engineering Report |
May 31, 2017 | Typist for Processing |
May 31, 2017 | Executive Sign Off |
May 31, 2017 | Sent to Photo Copy |
May 31, 2017 | Permit Approved |