Action Date | Action Description |
---|---|
Dec 05, 2017 | Assent Application Received |
Dec 05, 2017 | Administrative Review for Completeness |
Dec 06, 2017 | Team Review for Completeness |
Dec 06, 2017 | Application Accepted |
Dec 07, 2017 | Biologist Report |
Dec 08, 2017 | Typist for Processing |
Dec 08, 2017 | Executive Sign Off |
Dec 08, 2017 | Sent to Photo Copy |
Dec 08, 2017 | Permit Approved |
Dec 26, 2017 | Land Evidence Date |
Jan 08, 2018 | HPHC Historical Preservation No Effect |
Jul 09, 2018 | Modification Request |
Jul 10, 2018 | Administrative Review for Completeness |
Jul 11, 2018 | Team Review for Completeness |
Jul 12, 2018 | Application Accepted |
Jul 19, 2018 | Biologist Report |
Jul 20, 2018 | Typist for Processing |
Jul 20, 2018 | Executive Sign Off |
Jul 20, 2018 | Sent to Photo Copy |
Jul 20, 2018 | Modification Approved |
Jul 24, 2018 | HPHC Historical Preservation No Effect |
Aug 07, 2018 | Land Evidence Date |