Action Date |
Action Description |
Dec 13, 2017 |
Assent Application Received |
Dec 13, 2017 |
Administrative Review for Completeness |
Dec 14, 2017 |
Category A* (Docks) |
Dec 14, 2017 |
Team Review for Completeness |
Dec 14, 2017 |
Application Accepted |
Jan 08, 2018 |
HPHC Historical Preservation No Effect |
Jan 09, 2018 |
30 day Public Notice Issued |
Jan 31, 2018 |
Objections/Comments Received |
Feb 05, 2018 |
Objections/Comments Received |
Feb 10, 2018 |
Public Notice End Date |
Mar 22, 2018 |
Correspondence Mailed/Faxed/E-mailed |
May 17, 2018 |
30-Day Notification of Cancellation letter |
Jun 15, 2018 |
Correspondence Received |
Jun 28, 2018 |
Additional Information Requested from Applicant |
Aug 27, 2018 |
Plans Received |
Oct 24, 2018 |
Entry of Appearance Received |
Dec 06, 2018 |
Correspondence Received |
Jan 24, 2019 |
Comments Received |
Jan 25, 2019 |
Comments Received |
Feb 06, 2019 |
Additional Information Received |
Feb 13, 2019 |
Objections/Comments Received |
May 07, 2019 |
Additional Information Received |
May 30, 2019 |
Additional Information Requested from Applicant |
Jul 24, 2019 |
Additional Information Requested from Applicant |
Oct 15, 2019 |
Correspondence Mailed/Faxed/E-mailed |
Sep 17, 2020 |
Additional Information Received |
Sep 22, 2020 |
Additional Information Received |
Oct 01, 2020 |
Plans Received |
Jan 21, 2021 |
Additional Information Requested from Applicant |
Mar 01, 2021 |
Plans Received |
Mar 30, 2021 |
Correspondence Received |
Mar 30, 2021 |
Correspondence Mailed/Faxed/E-mailed |
Apr 29, 2021 |
Correspondence Mailed/Faxed/E-mailed |
May 06, 2021 |
Biologist Report |
May 10, 2022 |
Semi-Monthly Meeting Date Scheduled |
May 24, 2022 |
Semi-Monthly Meeting Date Scheduled |
Jun 08, 2022 |
Mail Agenda Notice |
Jun 30, 2022 |
Council Approval Granted |
Jun 30, 2022 |
Semi-Monthly Meeting Date Scheduled |
Jul 06, 2022 |
Stipulation Package from Biologist |
Sep 06, 2022 |
Additional Information Received |
Sep 13, 2022 |
Legal Response/Decision |
Sep 20, 2022 |
Permit Mailed |
Sep 20, 2022 |
Typist for Processing |
Sep 20, 2022 |
Executive Sign Off |
Sep 20, 2022 |
Sent to Photo Copy |
Sep 20, 2022 |
Permit Mailed |
Sep 20, 2022 |
Permit Approved |
Sep 28, 2022 |
Land Evidence Date |
Feb 21, 2023 |
Dock Post-Construction Certification by Engineer received. |