Action Date | Action Description |
---|---|
Feb 12, 2018 | Assent Application Received |
Feb 12, 2018 | Administrative Review for Completeness |
Feb 13, 2018 | Team Review for Completeness |
Feb 13, 2018 | Application Accepted |
Feb 26, 2018 | HPHC Historical Preservation No Effect |
Mar 08, 2018 | Plans Received |
Mar 09, 2018 | 30 day Public Notice Issued |
Apr 09, 2018 | Public Notice End Date |
Apr 17, 2018 | Additional Information Received |
Apr 19, 2018 | Executive Signoff of Staff Reports |
Apr 19, 2018 | Biologist Report |
Apr 19, 2018 | Mail Agenda Notice |
May 08, 2018 | Semi-Monthly Meeting Postponed |
May 08, 2018 | Semi-Monthly Meeting Date Scheduled |
May 08, 2018 | Mail Agenda Notice |
May 10, 2018 | Correspondence Mailed/Faxed/E-mailed |
May 21, 2018 | Mail Agenda Notice |
May 22, 2018 | Semi-Monthly Meeting Postponed |
May 22, 2018 | Semi-Monthly Meeting Date Scheduled |
Jun 12, 2018 | Semi-Monthly Meeting Date Scheduled |
Jun 12, 2018 | US Army Corps of Engineers Approval Received |
Jun 12, 2018 | Council Approval Granted |
Jul 09, 2018 | Legal Response/Decision |
Jul 11, 2018 | Stipulation Package from Biologist |
Jul 13, 2018 | Stipulation Package by Engineer |
Jul 13, 2018 | Typist for Processing |
Jul 13, 2018 | Category B assigned |
Jul 13, 2018 | Executive Sign Off |
Jul 13, 2018 | Sent to Photo Copy |
Jul 13, 2018 | Permit Approved |
Jul 20, 2018 | Land Evidence Date |
Aug 01, 2019 | Correspondence Received |