Action Date | Action Description |
---|---|
May 25, 2018 | Assent Application Received |
May 27, 2018 | Administrative Review for Completeness |
Jun 14, 2018 | Team Review for Completeness |
Jun 14, 2018 | Application Accepted |
Jun 18, 2018 | Policy Review |
Jun 26, 2018 | HPHC Historical Preservation No Effect |
Jul 09, 2018 | Permit Approved |
Jul 09, 2018 | Typist for Processing |
Jul 09, 2018 | Executive Sign Off |
Jul 09, 2018 | Sent to Photo Copy |
Jul 16, 2018 | Land Evidence Date |
Dec 19, 2019 | Monitoring Report |
Nov 25, 2020 | Monitoring Report |
Nov 18, 2021 | Monitoring Report |
Dec 02, 2021 | Assent Requirement |
Nov 04, 2022 | Monitoring Report |
Oct 18, 2023 | Monitoring Report |