Action Date | Action Description |
---|---|
Assent Requirement | |
Jun 04, 2018 | Maintenance Certification Request |
Jun 04, 2018 | Administrative Review for Completeness |
Jun 21, 2018 | Team Review for Completeness |
Jun 21, 2018 | Meeting Held |
Jun 21, 2018 | Deficient Application Picked Up |
Aug 14, 2018 | Deficiency Response Received |
Sep 05, 2018 | Team Review for Completeness |
Sep 05, 2018 | Application Accepted |
Sep 18, 2018 | HPHC Historical Preservation No Effect |
Mar 28, 2019 | Category A assigned |
Mar 28, 2019 | Typist for Processing |
Mar 28, 2019 | Executive Sign Off |
Mar 28, 2019 | Sent to Photo Copy |
Mar 28, 2019 | Permit Approved |
Mar 28, 2019 | Biologist Report |
Apr 05, 2019 | Land Evidence Date |
Oct 28, 2022 | Correspondence Mailed/Faxed/E-mailed |