Action Date | Action Description |
---|---|
Jun 05, 2018 | Maintenance Certification Request |
Jun 06, 2018 | Administrative Review for Completeness |
Jul 03, 2018 | Team Review for Completeness |
Jul 03, 2018 | Application Accepted |
Jul 13, 2018 | HPHC Historical Preservation No Effect |
Sep 20, 2018 | Biologist Report |
Sep 20, 2018 | Engineering Report |
Sep 20, 2018 | Typist for Processing |
Sep 20, 2018 | Permit Approved |
Oct 05, 2018 | Assent Correction Mailed |
Oct 26, 2018 | Land Evidence Date |