Action Date | Action Description |
---|---|
Jun 13, 2018 | Assent Application Received |
Jun 13, 2018 | Administrative Review for Completeness |
Jun 14, 2018 | Team Review for Completeness |
Jun 14, 2018 | Application Accepted |
Jun 26, 2018 | HPHC Historical Preservation No Effect |
Jul 17, 2018 | Plans Received |
Aug 02, 2018 | Joint Public Notice |
Sep 04, 2018 | Public Notice End Date |
Sep 21, 2018 | Dredge Report |
Sep 24, 2018 | Mail Agenda Notice |
Oct 05, 2018 | DEM Dredge Permit |
Oct 09, 2018 | Semi-Monthly Meeting Date Scheduled |
Oct 10, 2018 | Council Approval Granted |
Oct 11, 2018 | Legal Response/Decision |
Oct 16, 2018 | Typist for Processing |
Oct 16, 2018 | Executive Sign Off |
Oct 16, 2018 | Sent to Photo Copy |
Oct 16, 2018 | Permit Approved |
Oct 16, 2018 | Stipulation Package by Engineer |
Oct 22, 2018 | Land Evidence Date |
Oct 31, 2018 | US Army Corps of Engineers Approval Received |