Action Date | Action Description |
---|---|
Plans Received | |
Dock Post-Construction Certification by Engineer received. | |
Jun 19, 2018 | Assent Application Received |
Jun 19, 2018 | Administrative Review for Completeness |
Jun 26, 2018 | Team Review for Completeness |
Jun 26, 2018 | Application Accepted |
Jun 26, 2018 | Additional Information Requested from Applicant |
Jul 10, 2018 | 30 day Public Notice Issued |
Jul 13, 2018 | HPHC Historical Preservation No Effect |
Aug 07, 2018 | Additional Information Requested from Applicant |
Aug 10, 2018 | Public Notice End Date |
Sep 28, 2018 | Additional Information Requested from Applicant |
Oct 15, 2018 | Additional Information Requested from Applicant |
Nov 29, 2018 | Meeting Held |
Mar 03, 2019 | Additional Information Received |
Apr 11, 2019 | Meeting Held |
Apr 26, 2019 | Additional Information Received |
Jul 23, 2019 | Additional Information Received |
Jul 23, 2019 | Conservation Easement Recording received |
Jul 31, 2019 | Biologist Report |
Jul 31, 2019 | Engineering Report |
Aug 02, 2019 | Typist for Processing |
Aug 02, 2019 | Executive Sign Off |
Aug 02, 2019 | Sent to Photo Copy |
Aug 02, 2019 | Permit Approved |
Aug 08, 2019 | Land Evidence Date |