Action Date | Action Description |
---|---|
Sep 26, 2018 | Buffer Zone Management Application Received |
Sep 26, 2018 | Administrative Review for Completeness |
Oct 02, 2018 | Team Review for Completeness |
Oct 02, 2018 | Application Accepted |
Oct 17, 2018 | Additional Information Requested from Applicant |
Dec 18, 2018 | 30-Day Notification of Cancellation letter |
Jan 07, 2019 | Additional Information Received |
Jan 14, 2019 | Biologist Report |
Jan 17, 2019 | Typist for Processing |
Jan 17, 2019 | Executive Sign Off |
Jan 17, 2019 | Sent to Photo Copy |
Jan 17, 2019 | Permit Approved |