Action Date | Action Description |
---|---|
Dec 04, 2018 | Assent Application Received |
Dec 04, 2018 | Administrative Review for Completeness |
Dec 11, 2018 | Team Review for Completeness |
Dec 11, 2018 | Application Accepted |
Dec 11, 2018 | Category A* (Docks) |
Jan 07, 2019 | HPHC Historical Preservation No Effect |
Jan 14, 2019 | 30 day Public Notice Issued |
Feb 14, 2019 | Public Notice End Date |
Feb 21, 2019 | Comments Received |
Mar 04, 2019 | Additional Information Received |
Mar 05, 2019 | Additional Information Received |
Apr 08, 2019 | Comments Received |
May 02, 2019 | Meeting Held |
May 02, 2019 | Dock Meeting -- Approval |
May 06, 2019 | Biologist Report |
May 09, 2019 | Engineering Report |
May 09, 2019 | Typist for Processing |
May 09, 2019 | Executive Sign Off |
May 09, 2019 | Sent to Photo Copy |
May 09, 2019 | Permit Approved |
May 14, 2019 | Land Evidence Date |
Sep 30, 2019 | Dock Post-Construction Certification by Engineer received. |
Dec 26, 2019 | Comments Received |