Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Dec 26, 2018 | Assent Application Received |
Dec 26, 2018 | Administrative Review for Completeness |
Dec 27, 2018 | Team Review for Completeness |
Dec 27, 2018 | Application Accepted |
Jan 02, 2019 | 30 day Public Notice Issued |
Jan 16, 2019 | HPHC Historical Preservation No Effect |
Jan 16, 2019 | HPHC Review Pending |
Jan 23, 2019 | Comments Received |
Feb 02, 2019 | Public Notice End Date |
Apr 25, 2019 | Additional Information Received |
Apr 30, 2019 | Additional Information Received |
May 02, 2019 | Dock Meeting -- Approval |
May 08, 2019 | Biologist Report |
May 10, 2019 | Typist for Processing |
May 10, 2019 | Executive Sign Off |
May 10, 2019 | Sent to Photo Copy |
May 10, 2019 | Permit Approved |
May 20, 2019 | Land Evidence Date |
Nov 05, 2019 | Correspondence Mailed/Faxed/E-mailed |
Nov 05, 2019 | Correspondence Mailed/Faxed/E-mailed |
Nov 06, 2019 | Permit Rescinded |
Nov 09, 2019 | Certified Receipt Received |
May 19, 2020 | Note to File |
May 19, 2020 | Permit Approved |
Nov 27, 2023 | Land Evidence Date |
Dec 07, 2023 | Correspondence Received |