Action Date | Action Description |
---|---|
Jan 25, 2019 | Assent Application Received |
Jan 25, 2019 | Administrative Review for Completeness |
Jan 25, 2019 | Team Review for Completeness |
Jan 25, 2019 | Category A* (Docks) |
Jan 28, 2019 | Application Accepted |
Jan 30, 2019 | 30 day Public Notice Issued |
Feb 14, 2019 | HPHC Review Pending |
Feb 14, 2019 | HPHC Historical Preservation No Effect |
Mar 01, 2019 | Public Notice End Date |
May 20, 2019 | Plans Received |
Jun 07, 2019 | Biologist Report |
Jun 11, 2019 | Supervisor Biologist SignOff |
Jun 11, 2019 | Supervisor Engineer SignOff |
Jun 11, 2019 | Executive Signoff of Staff Reports |
Jul 11, 2019 | Ready to Schedule Semi-Monthly Meeting |
Jul 11, 2019 | Mail Agenda Notice |
Jul 23, 2019 | Council Approval Granted |
Jul 23, 2019 | Semi-Monthly Meeting Date Scheduled |
Aug 02, 2019 | Legal Response/Decision |
Aug 02, 2019 | 30 Day Appeal Notification to Owner |
Aug 13, 2019 | Plans Received |
Aug 15, 2019 | Stipulation Package from Biologist |
Aug 16, 2019 | Typist for Processing |
Aug 16, 2019 | Executive Sign Off |
Aug 16, 2019 | Sent to Photo Copy |
Aug 16, 2019 | Permit Approved |
Sep 09, 2019 | Land Evidence Date |
Nov 05, 2019 | Assent Requirement |