Action Date | Action Description |
---|---|
Apr 29, 2019 | Assent Application Received |
Apr 29, 2019 | Administrative Review for Completeness |
Apr 30, 2019 | Team Review for Completeness |
Apr 30, 2019 | Application Accepted |
May 10, 2019 | HPHC Review Pending |
May 10, 2019 | HPHC Historical Preservation No Effect |
Jun 26, 2019 | 30 day Public Notice Issued |
Jul 26, 2019 | Public Notice End Date |
Aug 02, 2019 | Dock/1.1.6 Review approval |
Aug 08, 2019 | Plans Received |
Aug 21, 2019 | Comments Received |
Sep 20, 2019 | Typist for Processing |
Sep 20, 2019 | Executive Sign Off |
Sep 20, 2019 | Sent to Photo Copy |
Sep 20, 2019 | Permit Approved |
Sep 20, 2019 | Biologist Report |
Sep 26, 2019 | US Army Corps of Engineers Approval Received |
Oct 08, 2019 | Land Evidence Date |
Jun 10, 2020 | Modification Request |
Jun 15, 2020 | Administrative Review for Completeness |
Jul 20, 2020 | Plans Received |
Jul 22, 2020 | Bio Team Review for Completeness |
Jul 23, 2020 | Project Manager |
Jul 31, 2020 | Category A* (Docks) |
Jul 31, 2020 | 30 day Public Notice Issued |
Aug 11, 2020 | Comments Received |
Aug 30, 2020 | Public Notice End Date |
Oct 14, 2020 | Dock Meeting Scheduled (Admin) |
Oct 23, 2020 | Typist for Processing |
Oct 23, 2020 | Executive Sign Off |
Oct 23, 2020 | Sent to Photo Copy |
Oct 23, 2020 | Modification Approved |
Oct 23, 2020 | Engineering Report |
Nov 06, 2020 | Land Evidence Date |
Mar 01, 2021 | Dock Post-Construction Certification by Engineer received. |