Action Date | Action Description |
---|---|
Monitoring Report | |
Under Review/Decision | |
Jun 12, 2019 | Assent Application Received |
Jun 12, 2019 | Administrative Review for Completeness |
Jun 14, 2019 | Team Review for Completeness |
Jun 14, 2019 | Application Accepted |
Jun 14, 2019 | Category B assigned |
Jul 03, 2019 | HPHC Historical Preservation No Effect |
Jul 03, 2019 | HPHC Review Pending |
Jul 23, 2019 | 30 day Public Notice Issued |
Jul 31, 2019 | Notice Advertisement confirmation |
Aug 20, 2019 | Objections/Comments Received |
Aug 23, 2019 | Public Notice End Date |
Aug 25, 2019 | Letter of Support for Project |
Sep 20, 2019 | Public Hearing Notices Mailed |
Sep 25, 2019 | Biologist Report |
Sep 25, 2019 | Engineering Report |
Sep 26, 2019 | Notice Advertisement confirmation |
Oct 08, 2019 | Semi-Monthly Meeting Date Scheduled |
Oct 08, 2019 | Council Approval Granted |
Oct 08, 2019 | Public Hearing Scheduled |
Feb 26, 2020 | Stipulation Package by Engineer |
Feb 27, 2020 | Stipulation Package from Biologist |
Mar 05, 2020 | Legal Response/Decision |
Mar 09, 2020 | Executive Sign Off |
Mar 09, 2020 | Sent to Photo Copy |
Mar 09, 2020 | Permit Approved |
Mar 09, 2020 | Typist for Processing |
Apr 17, 2020 | Land Evidence Date |
Mar 08, 2023 | US Army Corps of Engineers Approval Received |
Nov 07, 2023 | Meeting Held |
Dec 14, 2023 | Meeting Held |
Feb 14, 2024 | Meeting Held |
Feb 15, 2024 | Correspondence Mailed/Faxed/E-mailed |
Mar 15, 2024 | Correspondence Mailed/Faxed/E-mailed |
Apr 05, 2024 | Correspondence Received |