Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Aug 19, 2019 | Assent Application Received |
Aug 20, 2019 | Administrative Review for Completeness |
Sep 18, 2019 | Team Review for Completeness |
Sep 18, 2019 | Deficient Application - Owner Notification Sent |
Oct 21, 2019 | Deficiency Response Received |
Oct 21, 2019 | HPHC Review Pending |
Oct 23, 2019 | Application Accepted |
Oct 23, 2019 | Bio Team Review for Completeness |
Oct 28, 2019 | Plans Received |
Nov 07, 2019 | HPHC Historical Preservation No Effect |
Nov 07, 2019 | HPHC Review Pending |
Apr 02, 2020 | Public Notice End Date |
Apr 07, 2020 | Dock/1.1.6 Review approval |
Apr 07, 2020 | Category A* (Docks) |
Apr 10, 2020 | Correspondence Mailed/Faxed/E-mailed |
Jun 17, 2020 | Correspondence Mailed/Faxed/E-mailed |
Oct 07, 2020 | Correspondence Received |
Oct 19, 2020 | Correspondence Mailed/Faxed/E-mailed |
Oct 19, 2020 | Correspondence Received |
Dec 15, 2020 | Correspondence Mailed/Faxed/E-mailed |
Dec 15, 2020 | Plans Received |
Dec 16, 2020 | Correspondence Mailed/Faxed/E-mailed |
Dec 16, 2020 | Correspondence Received |
Dec 18, 2020 | Plans Received |
Dec 18, 2020 | Correspondence Mailed/Faxed/E-mailed |
Dec 18, 2020 | Plans Received |
Jan 29, 2021 | US Army Corps of Engineers Approval Received |
Mar 29, 2021 | Plans Received |
Apr 15, 2021 | Plans Received |
Apr 16, 2021 | Stipulation Package from Biologist |
Apr 16, 2021 | Stipulation Package by Engineer |
Apr 16, 2021 | Typist for Processing |
Apr 16, 2021 | Permit Approved |
Apr 16, 2021 | Executive Sign Off |
Apr 16, 2021 | Engineering Report |
Apr 16, 2021 | Biologist Report |
Jun 03, 2021 | Land Evidence Date |