Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Oct 16, 2019 | Assent Application Received |
Oct 16, 2019 | Administrative Review for Completeness |
Oct 29, 2019 | Deficient Application - Owner Notification Sent |
Nov 13, 2019 | Deficiency Response Received |
Nov 13, 2019 | Bio Team Review for Completeness |
Nov 21, 2019 | Eng Team Review for Completeness |
Nov 21, 2019 | Application Accepted |
Nov 21, 2019 | Bio Team Review for Completeness |
Dec 04, 2019 | 30 day Public Notice Issued |
Dec 05, 2019 | HPHC Historical Preservation No Effect |
Dec 05, 2019 | HPHC Review Pending |
Jan 04, 2020 | Public Notice End Date |
Feb 05, 2020 | Plans Received |
Apr 07, 2020 | Dock/1.1.6 Review approval |
May 05, 2020 | Typist for Processing |
May 05, 2020 | Executive Sign Off |
May 05, 2020 | Sent to Photo Copy |
May 05, 2020 | Permit Approved |
May 05, 2020 | Engineering Report |
Aug 11, 2020 | Land Evidence Date |