Action Date | Action Description |
---|---|
Nov 25, 2019 | Assent Application Received |
Nov 25, 2019 | Administrative Review for Completeness |
Dec 06, 2019 | Bio Team Review for Completeness |
Dec 06, 2019 | Eng Team Review for Completeness |
Dec 06, 2019 | Application Accepted |
Feb 17, 2020 | Joint Public Notice |
Feb 18, 2020 | HPHC Review Pending |
Feb 18, 2020 | HPHC Historical Preservation No Effect |
Mar 16, 2020 | Letter of Support for Project |
Mar 16, 2020 | Letter of Support for Project |
Mar 17, 2020 | Public Notice End Date |
Jun 05, 2020 | Additional Information Received |
Jun 19, 2020 | Letter of Support for Project |
Aug 12, 2020 | Letter of Support for Project |
Aug 18, 2020 | Additional Information Received |
Sep 24, 2020 | Water Quality Certification |
Sep 29, 2020 | Ready to Schedule Semi-Monthly Meeting |
Sep 29, 2020 | Mail Agenda Notice |
Oct 02, 2020 | Engineering Report |
Oct 06, 2020 | Biologist Report |
Oct 13, 2020 | Semi-Monthly Meeting Date Scheduled |
Oct 19, 2020 | Council Approval Granted |
Oct 27, 2020 | Stipulation Package by Engineer |
Oct 27, 2020 | Typist for Processing |
Oct 27, 2020 | Executive Sign Off |
Oct 27, 2020 | Sent to Photo Copy |
Oct 27, 2020 | Permit Approved |
Nov 03, 2020 | Land Evidence Date |
Apr 07, 2023 | Comments Received |
Aug 28, 2023 | Extension of Permit Request |
Nov 29, 2023 | Enforcement Compliance Inspection Required |
Dec 01, 2023 | Process Extension |
Dec 01, 2023 | Typist for Processing |
Dec 01, 2023 | Executive Sign Off |
Dec 01, 2023 | Sent to Photo Copy |
Dec 01, 2023 | Extension Approved |