Action Date | Action Description |
---|---|
Dec 16, 2019 | Assent Application Received |
Dec 16, 2019 | Administrative Review for Completeness |
Dec 18, 2019 | Bio Team Review for Completeness |
Jan 06, 2020 | Eng Team Review for Completeness |
Jan 06, 2020 | Application Accepted |
Feb 10, 2020 | HPHC Historical Preservation No Effect |
Feb 10, 2020 | HPHC Review Pending |
Mar 13, 2020 | Plans Received |
May 04, 2020 | Typist for Processing |
May 04, 2020 | Executive Sign Off |
May 04, 2020 | Sent to Photo Copy |
May 04, 2020 | Permit Approved |
May 04, 2020 | Engineering Report |
May 21, 2020 | Land Evidence Date |