Action Date | Action Description |
---|---|
Jan 29, 2020 | Freshwater Wetland - Preliminary Determination |
Jan 29, 2020 | Administrative Review for Completeness |
Feb 06, 2020 | Bio Team Review for Completeness |
Feb 06, 2020 | Deficient Application - Owner Notification Sent |
Feb 13, 2020 | Deficiency Response Received |
Feb 13, 2020 | Bio Team Review for Completeness |
Feb 13, 2020 | Application Accepted |
Feb 25, 2020 | HPHC Review Pending |
Feb 25, 2020 | HPHC Historical Preservation No Effect |
Mar 27, 2020 | Additional Information Requested from Applicant |
Apr 22, 2020 | Additional Information Received |
Jun 24, 2020 | Additional Information Requested from Applicant |
Jul 20, 2020 | Correspondence Received |
Oct 02, 2020 | 30-Day Notification of Cancellation letter |
Oct 15, 2020 | Correspondence Received |
Oct 22, 2020 | Additional Information Received |
Oct 29, 2020 | Correspondence Mailed/Faxed/E-mailed |
Jan 14, 2021 | Additional Information Requested from Applicant |
Mar 15, 2021 | 30-Day Notification of Cancellation letter |
Mar 30, 2021 | Additional Information Received |
Apr 06, 2021 | Additional Information Requested from Applicant |
Apr 12, 2021 | Plans Received |
Apr 26, 2021 | Stipulation Package from Biologist |
Apr 26, 2021 | Typist for Processing |
Apr 26, 2021 | Executive Sign Off |
Apr 26, 2021 | Permit Approved |
Apr 26, 2021 | Biologist Report |
May 11, 2021 | Land Evidence Date |