Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Assent Requirement | |
Feb 24, 2020 | Assent Application Received |
Feb 25, 2020 | Administrative Review for Completeness |
Mar 05, 2020 | Bio Team Review for Completeness |
Mar 06, 2020 | Deficient Application - Owner Notification Sent |
Mar 10, 2020 | Deficient Application Picked Up |
Apr 22, 2020 | Deficiency Response Received |
Apr 23, 2020 | Bio Team Review for Completeness |
Apr 23, 2020 | Application Accepted |
Apr 23, 2020 | Project Manager |
Apr 27, 2020 | HPHC Historical Preservation No Effect |
Apr 28, 2020 | Additional Information Requested from Applicant |
May 18, 2020 | Plans Received |
Jun 04, 2020 | Typist for Processing |
Jun 04, 2020 | Permit Approved |
Jun 04, 2020 | Executive Sign Off |
Jun 04, 2020 | Sent to Photo Copy |
Jun 04, 2020 | Biologist Report |
Aug 12, 2020 | Land Evidence Date |