Action Date | Action Description |
---|---|
Mar 02, 2020 | Maintenance Certification Request |
Mar 02, 2020 | Administrative Review for Completeness |
Mar 04, 2020 | Eng Team Review for Completeness |
Mar 04, 2020 | Application Accepted |
Sep 29, 2020 | Application Cancelled |
Sep 29, 2020 | Engineering Report |
Aug 18, 2021 | Biologist Report |
Aug 18, 2021 | Stipulation Package from Biologist |
Aug 20, 2021 | Typist for Processing |
Aug 20, 2021 | Executive Sign Off |
Aug 20, 2021 | Sent to Photo Copy |
Aug 20, 2021 | Permit Approved |
Aug 24, 2021 | Permit Mailed |