Action Date | Action Description |
---|---|
Mar 05, 2020 | Assent Application Received |
Mar 06, 2020 | Administrative Review for Completeness |
Mar 06, 2020 | Bio Team Review for Completeness |
Mar 06, 2020 | Project Manager |
Mar 06, 2020 | Application Accepted |
Mar 31, 2020 | Additional Information Received |
Mar 31, 2020 | Additional Information Requested from Applicant |
Apr 02, 2020 | HPHC Historical Preservation Comments/Concerns |
Apr 07, 2020 | Correspondence Received |
Apr 07, 2020 | Additional Information Received |
May 04, 2020 | HPHC Historical Preservation Comments/Concerns |
May 05, 2020 | Correspondence Received |
May 06, 2020 | HPHC Historical Preservation No Effect |
May 06, 2020 | HPHC Review Pending |
May 20, 2020 | Biologist Report |
May 21, 2020 | Typist for Processing |
May 21, 2020 | Executive Sign Off |
May 21, 2020 | Sent to Photo Copy |
May 21, 2020 | Permit Approved |
May 28, 2020 | Land Evidence Date |