Action Date | Action Description |
---|---|
Mar 06, 2020 | Buffer Zone Management Application Received |
Mar 10, 2020 | Administrative Review for Completeness |
Mar 17, 2020 | Bio Team Review for Completeness |
Mar 17, 2020 | Application Accepted |
Mar 17, 2020 | Project Manager |
Mar 24, 2020 | HPHC Historical Preservation No Effect |
Mar 24, 2020 | HPHC Review Pending |
Apr 20, 2020 | Additional Information Received |
May 11, 2020 | Biologist Report |
May 12, 2020 | Permit Approved |
May 12, 2020 | Typist for Processing |
Nov 09, 2023 | Monitoring Report |