Action Date | Action Description |
---|---|
Mar 12, 2020 | Bio Team Review for Completeness |
Mar 12, 2020 | Assent Application Received |
Mar 12, 2020 | Administrative Review for Completeness |
Mar 16, 2020 | Project Manager |
Mar 16, 2020 | Application Accepted |
Mar 19, 2020 | HPHC Historical Preservation No Effect |
Mar 19, 2020 | HPHC Review Pending |
Apr 23, 2020 | Project Manager |
Apr 23, 2020 | Typist for Processing |
Apr 23, 2020 | Executive Sign Off |
Apr 23, 2020 | Sent to Photo Copy |
Apr 23, 2020 | Permit Approved |
Apr 23, 2020 | Biologist Report |
May 13, 2020 | Land Evidence Date |