Action Date | Action Description |
---|---|
Executive Sign Off | |
Sent to Photo Copy | |
Mar 12, 2020 | Assent Application Received |
Mar 13, 2020 | Administrative Review for Completeness |
Mar 16, 2020 | Bio Team Review for Completeness |
Mar 16, 2020 | Project Manager |
Mar 16, 2020 | Application Accepted |
Mar 18, 2020 | Additional Information Received |
Apr 01, 2020 | Additional Information Requested from Applicant |
Apr 14, 2020 | HPHC Historical Preservation No Effect |
Apr 14, 2020 | HPHC Review Pending |
Apr 29, 2020 | Plans Received |
May 11, 2020 | Permit Approved |
May 11, 2020 | Typist for Processing |
May 11, 2020 | Biologist Report |
May 15, 2020 | Land Evidence Date |