Action Date | Action Description |
---|---|
Mar 19, 2020 | Dredge Application |
Mar 20, 2020 | Administrative Review for Completeness |
Mar 24, 2020 | Eng Team Review for Completeness |
Mar 24, 2020 | Application Accepted |
Mar 24, 2020 | Project Manager |
Mar 27, 2020 | Joint Public Notice |
Mar 30, 2020 | HPHC Historical Preservation No Effect |
Mar 31, 2020 | Comments Received |
Apr 27, 2020 | Public Notice End Date |
May 05, 2020 | Dredge Report |
May 06, 2020 | Executive Sign Off |
May 07, 2020 | Typist for Processing |
May 07, 2020 | Permit Approved |
May 07, 2020 | DEM Dredge Permit |
Dec 29, 2020 | Land Evidence Date |
Mar 17, 2022 | CAD Cell Fee Due - initial (letter) |
Mar 17, 2022 | CAD Cell Fee (initial) received |
Mar 17, 2022 | CAD Cell Fee Due-Final |