Action Date | Action Description |
---|---|
Mar 20, 2020 | Assent Application Received |
Mar 23, 2020 | Administrative Review for Completeness |
Apr 09, 2020 | Eng Team Review for Completeness |
Apr 09, 2020 | Project Manager |
Apr 09, 2020 | Application Accepted |
Apr 14, 2020 | HPHC Historical Preservation No Effect |
Apr 14, 2020 | HPHC Review Pending |
Jun 10, 2020 | Additional Information Received |
Jun 22, 2020 | Typist for Processing |
Jun 22, 2020 | Executive Sign Off |
Jun 22, 2020 | Sent to Photo Copy |
Jun 22, 2020 | Permit Approved |
Jun 22, 2020 | Engineering Report |
Jul 08, 2020 | Land Evidence Date |