Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Apr 09, 2020 | Assent Application Received |
Apr 13, 2020 | Administrative Review for Completeness |
Apr 13, 2020 | Bio Team Review for Completeness |
Apr 14, 2020 | Project Manager |
Apr 14, 2020 | Application Accepted |
Apr 14, 2020 | 30 day Public Notice Issued |
Apr 14, 2020 | Category A* (Docks) |
May 06, 2020 | HPHC Historical Preservation No Effect |
May 06, 2020 | HPHC Review Pending |
May 14, 2020 | Public Notice End Date |
May 27, 2020 | Dock Meeting -- Approval |
Jun 10, 2020 | Biologist Report |
Jun 11, 2020 | Typist for Processing |
Jun 11, 2020 | Executive Sign Off |
Jun 11, 2020 | Sent to Photo Copy |
Jun 11, 2020 | Permit Approved |
Sep 11, 2020 | Land Evidence Date |